Maintenance and repair of electrical equipment of power plants and switchgears
Dates - from June 14 to June 18; from December 06 to December 10
№ |
Section names |
Watch |
||
Total |
Lectures |
Practice |
||
|
Repair of windings and insulation of electrical equipment |
2 |
2 |
|
|
Repair of switchgear equipment |
2 |
2 |
- |
|
Testing of installed equipment |
2 |
2 |
- |
|
Checking thermal protection and automation devices |
2 |
2 |
- |
|
Installation and adjustment of emergency automation |
2 |
2 |
- |
|
Repair of high-voltage equipment |
4 |
4 |
- |
|
Repair of switching equipment |
2 |
2 |
- |
|
Repair of relay protection equipment |
2 |
2 |
- |
|
Checking and checking the parameters of the power transformer before switching on under load |
2 |
2 |
- |
|
Checking the synchronization of overhead and RF lines |
2 |
2 |
- |
|
Installation and commissioning of electrical equipment for repair |
4 |
4 |
- |
|
Classes at work |
8 |
- |
8 |
|
TOTAL |
36 |
28 |
8 |