1.1. Repair and adjustment of the switched power grid equipment with a voltage of 220 kV and above
Dates - from May 17 to May 28; from October 25 to November 05
№ |
Section names |
Watch |
||
Total |
Lectures |
Practice |
||
1 |
Scheduled preventive maintenance and repair of high-voltage switches and inputs |
6 |
6 |
|
2 |
Comprehensive measurements for diagnostics of high-voltage switches and inputs |
12 |
8 |
4 |
3 |
Installation and adjustment of high-voltage circuit breakers |
18 |
14 |
4 |
4 |
Maintenance of high-voltage circuit breakers |
12 |
12 |
- |
5 |
Features of the drives of the switches of the company "Siemens» |
8 |
8 |
- |
6 |
Diagnostics of substation switching equipment |
8 |
8 |
- |
7 |
Operational terms of diagnostics of high-voltage circuit breakers |
8 |
8 |
- |
|
TOTAL |
72 |
64 |
8 |